base layers storage does not meet Flow Control requirements underdrain system may required
| Table 1-1 Soil Characterization Chart
for Design of Permeable Surface Layers |
|||||
| Soil Type | A | B | C | D | Notes |
| Surface Layer | 1 - 4 (A) | 1 - 4 (A) | 1 - 4 (A) | 1 - 4 (A) | 4-inch depth (min.) |
| Base Layer | 5 | 5 | 5 | 5 | 6-inch depth (min.); 6, 7 & 8 may be considered for certain applications |
| Separation Layer | 9, 10 (B) | 9, 10 (B) | 9, 10 (B) | 9, 10 (B) | The use of “10 -Treatment Media Layer” shall not be used unless required |
| Sub-grade Soil | 11 | 11 | 11 | 11 | If sub-grade is overly compacted prior to constructing pavement, till soil 2-feet below the material placement to maintain the soil’s permeability |
Underdrain System |
No | No | To be determined | To be determined | 6-inch dia. (min.); discharged to bioretention area, natural dispersion or a detention facility |
Edge Treatment |
To be considered | To be considered | To be considered | To be considered | 6-inch dia. (min.); discharged to bioretention area, natural dispersion or a detention facility |
| Subgrade Slope | To be considered | To be considered | To be considered | To be considered | Consider slopes from 1.0% to 2.0% |
| Placement Application | 12 - 18 | 12 - 18 | 12 - 18 | 13 - 18 | |
NUMBERS REFERENCED IN TABLE 1-1:
|
NOTES REFERENCED IN TABLE 1-1:
(A) The separation of permeable surface installations from impermeable surface runoff may be necessary by installing an edge drain or a similar system.
(B) A treatment media layer is not required where subgrade soil is determined to have a long-term infiltration rate less than 2.4 inches per hour and a cation exchange capacity (CEC) of the subgrade soil that is at least 5 milli-equivalents CEC/ 100 grams of dry soil or greater (WSDOE, 2001).
(C) Shall meet the requirements stipulated in the January 3, 2002 FHWA Manual on Construction of Pavement Subsurface Drainage Systems publication number FHWA-IF-01-014 HIPA-20/1-02(500) for aggregate gradation, page 20 Table 2-1, with 75% minimum fracture. Other variances, other than fracture, from standard specifications 9-03.1(4)A and 9-03.1(4)B should be reviewed and included as applicable and as coordinated with the Materials Office, Roadway Design Office and Hydraulics Office. Blending of other aggregate gradations shall not be allowed.
(D) Shall meet the requirements stipulated in the January 3, 2002 FHWA Manual on Construction of Pavement Subsurface Drainage Systems publication number FHWA-IF-01-014 HIPA-20/1-02(500) for aggregate gradation, page 25 Table 2-3, with 75% minimum fracture. Table 2-4 can be used if the fracture requirement can be met. The 200-sieve variance in the previously referenced FHWA publication should not be exceeded. Other variances, other than fracture, from standard specifications 9-03.1(4)A and 9-03.1(4)B should be reviewed and included as applicable and as coordinated with the Materials Office, Roadway Design Office and Hydraulics Office. Blending of other aggregate gradations shall not be allowed.
(E) Permeable Geotextile shall be used to keep the surface layer stable and fines from migrating up through the surface and base layers. To obtain Geotextile classification use Geotextile for Underground Drainage, see WSDOT standard specification section 9-33.
(F) Shall meet the requirements stipulated in the January 3, 2002 FHWA Manual on Construction of Pavement Subsurface Drainage Systems publication number FHWA-IF-01-014 HIPA-20/1-02(500) for aggregate gradation.
(G) This design approach must seek approval from the Materials Office, Roadway Design Office, and the Hydraulics Office. Proposed placement applications shall only use type1 & 2 surface layers.
2. Soil Infiltration Rate
Once a permeable surface site is identified, contact the Region Materials Office to request that a Geotechnical investigation be performed. The Region Materials Office, with assistance from the Headquarters Geotechnical Branch as needed, will determine the quantity and depth of borings/test pits required and any ground water monitoring needed to characterize the soil infiltration characteristics of the site.
Design-level infiltration should be determined by using WSDOT’s “Interim Infiltration Design Guidance.” This process for determining the infiltration rate relies on the D10 of the tested soils (WSDOT, 2002). This guidance provides a correlation between the D10 size of the soils below the infiltration facility, as shown in Table 1-2. Note that this guidance applies primarily to infiltration basins and may, therefore, exclude slower-percolating soils such as loams, which are potentially suitable for permeable surfaces.
Table 1-2. Recommended Infiltration Rates based on ASTM Gradation Testing
| D10 Size from ASTM D422 Soil Gradation Test (mm) | Estimated Long-Term (Design) Infiltration Rate (in/hr) |
| > 0.4 | 9 |
| 0.3 | 6.5 |
| 0.2 | 3.5 |
| 0.1 | 2.0 |
| 0.05 | 0.8 |
An alternate method is to determine the soil textural classification for the project site (e.g., from soil survey or field data) and compare to the USDA Texture Triangular (Figure 1-1). For the underlying soil, use an infiltration rate as shown in Table 1-3. The infiltration rates derived from both of these methods are reasonably conservative. With the low hydraulic loading experienced by a permeable surface project (i.e., drainage area to infiltration area ratio of approximately 1:1 compared to approximately 100:1 for conventional infiltration basins), the risk resulting from an inaccurate infiltration value is low. Therefore, it is anticipated that infiltration testing may typically not be required for permeable surface projects. If it is required, the Pilot Infiltration Test (PIT) described in Appendix V-B of the Ecology Stormwater Manual for Western Washington (WSDOE, 2001) can be used.
Figure 1-1. Percentage of sand, silt, and clay in the major soil textural classes (USDA Texture Triangular).
Table 1-3. Estimated Infiltration Rate for Major Soil Textural Classes.
| Soil Textural Class | Estimated Infiltration Rate (inches/hour)* |
| Sand | 2.5 |
| Loamy sand | 1.5 |
| Silt | 1.3 |
| Sandy Loam | 0.8 |
| Silt Loam | 0.7 |
| Loam | 0.4 |
*From Saxton (2003).
3. Sizing of Infiltration Basin
In Western Washington use MGSFlood, the Western Washington Hydrology Model (WWHM) or other acceptable continuous runoff simulation model to size an infiltration basin. In this case, the bottom area of the “infiltration basin” will typically be the same as the area underlying the permeable surface. Vary the depth of the “infiltration basin” so it is sufficient to meet Flow Control requirements. This will be equivalent to the depth of water to be stored in the base material underlying the permeable surface.
A stormwater manual is currently being prepared for Eastern Washington. Hydrologic methods in that manual, when available, should be used for sites located in Eastern Washington. In the interim period, use an appropriate single event-based model consistent with infiltration design.
Multiply the stored water depth by a factor of 5. This will determine the depth of the gravel base underlying the permeable surface. This assumes a porosity of 0.20, a conservative assumption. When a base material that has a different porosity will be used, that value may be substituted to determine the depth of the base. The minimum base depth is 6-inches, which allows for adequate structural support of the permeable surface.
For a large, contiguous area of permeable surface, such as a parking lot, the area may be designed with a level surface grade and a sloped subgrade to prevent water buildup on the surface to occur, except under extreme conditions. Rare instances of shallow ponding in a parking lot are normally acceptable.
For projects where ponding is unacceptable under any condition, the surface of the parking lot may be graded at a one percent slope leading to a shallow swale, which would function to assure emergency drainage, similar to an emergency overflow from a conventional infiltration pond. However, the design depth of the base material must be maintained at all locations.
4. Construction Criteria
The key to successful installation of the permeable surface system is diligent attention to construction application techniques and proper inspection. Emphasis must be placed upon strict quality control measures during site preparation and the laying of the permeable surface. Experience has shown that most cases of failure can be traced to faulty construction. The Contractor should have previous experience in the construction of a permeable surface. In lieu of this experience, the Contractor should be required to construct two test panels of the permeable surface ahead of the main surface’s placement to demonstrate competency. These panels can then be tested to assure that the proper thickness, density, and porosity have been achieved.
Turbid off-site runoff to a project site where permeable surfaces are to be placed during construction should be avoided. Specifications should be included requiring protection of locations where permeable surfaces are to be placed. Should contamination of the permeable surface layers occur, a cleanup process in the contract should be stipulated requiring the contractor to remove all sediments or deleterious material in the areas designated by the engineer and to the engineers satisfaction.
- The ambient temperature during a permeable surface application should be higher than 40 degrees Fahrenheit.
- Roller consolidation, with no more than three passes, is adequate. Repeated passes and/or vibrating compactors may significantly reduce the void space and may damage the permeable surface, therefore, its permeability.
- Pervious concrete should be covered with a minimum of 6 mil of polyethylene sheeting for a minimum of 7 days after placement.
5. Maintenance Criteria
Permeable surfaces require more maintenance than conventional pavement installations. The primary concern in maintaining the continued effectiveness of a permeable surface system is to prevent the surface from clogging with fine sediments and debris.
- Permeable surfaces will clog if improperly maintained. Maintenance or cleanup within the permeable surface layer should include the use of localized high pressure vacuuming. Maintenance should include the scheduled use of vacuum street sweepers and other practices to remove or prevent leaves, needles, or other foliage from collecting on the surface layer.
- Should clogging occur, it is usually limited to a specific area. Remedies include localized vacuuming followed by power washing. In severe cases, the clogged area may need to be removed and reconstructed. Maintenance levels will generally vary depending on the potential likelihood of fine sediments clogging the surface. Sites with a higher risk of clogging due to extensive numbers of nearby trees, high traffic volumes, or high dust levels may require that the pavement surfaces be cleaned more frequently.
- Signs should be posted on the site identifying permeable surface areas to aid maintenance crews and inform the public. This also assures that periodic resurfacing will be done in a manner that maintains the permeable surface.
- Regular inspections following rainstorms and active preventive maintenance practices are important.
- If spills occur, they should be immediately vacuumed up followed by a pressure wash or other appropriate rinse procedure.
D. Preliminary Drawings and Specifications
A preliminary standard drawing for pervious pavement has been prepared and is attached. Three Special Provisions for permeable surfaces have been prepared and are attached:
- SP 2-06.2, Aggregate for Pervious Paving and Base
- SP 5-04, Asphaltic Pervious Concrete
- SP 5-05, Portland Cement Pervious Concrete
E. Permeable Surfacing References
- Brattebo, B. and Derek Booth. 2002. Permeable Parking Lot Demonstration Project—the Six-Year Follow-Up. In The Washington Water Resource-Vol. 10, No. 3., University of Washington, Seattle, Washington.
- Chollack, Tracy, et al. 2001. Porous Pavement Phase 1 Evaluation Report. Seattle Public Utilities, Report, Seattle, Washington, February 7, 2001.
- Federal Highway Administration. 2002. Construction of Pavement Subsurface Drainage Systems. Publication FHWA IF-01-014. Washington, D.C.
- Huber, G. 2000. Performance Survey on Open-Graded Friction Course Mixes, Synthesis of Highway Practice. No. 284, National Academy Press. Washington, D.C.
- Mallick, R.B. et al. 2000. Design, Construction and Performance of New-Generation Open-Graded Friction Courses. National Center for Asphalt Technology. Auburn university, Alabama.
- Newman, A. P. et al. 2002. Oil Retention and Microbial Ecology in Porous Pavement Structures. Coventry University. Coventry, England.
- North Carolina State University. 2000. Hydraulic Design for Permeable Pavement—Workshop. Department of Biological and Agricultural Engineering, Raleigh, North Carolina.
- Paine, Jack. 1992. Portland Cement Pervious Pavement Construction, Publication #C920655, The Aberdeen Group.
- Saxton, K.E. 2003. Soil Water Characteristics – Hydraulic Properties Calculator. Web Address: http://www.bsyse.wsu.edu/saxton/soilwater/ Washington State University-USDA Agricultural Research Service, Pullman, Washington.
- SMRC. 2002a. Stormwater Management Fact Sheet: Porous Pavement. The Stormwater Manager’s Resource Center, http://www.stormwatercenter.net/
- WSDOE (Washington State Department of Ecology). 2001. Stormwater Management Manual for Western Washington. Olympia, Washington.
- WSDOT (Washington State Department of Transportation). 2002. Project Delivery Memo #02-03- Interim .
See all the reviews